Information on Recovery Works Process in the House 53/28 in Naberezhnye Chelny as of July 18, 9.00 A.M.

18 July 2016, Monday

During July 18, the following activities were held:

- works on the evaluation of the building for damage of bearing structures proceeded;

- works on strengthening bearing structures of the ceiling between the basement and the ground floor continue;

- with the cumulative total, 52 windows have been repaired (85% completed);

- recovery works of the lift in the 2nd entrance are complete;

- recovery works of electric wiring and power meters in ectroboards are complete;

- gas pipes in the 2nd entrance are pressurized.

96 people, including 23 children, live in a temporary accommodation center on the basis of “KamAZ” hotel. Three meals a day are provided, there was organized the duty of an employee from the 15th squad of Federal Fire Service.

24 people, including 2 children, are accommodated in relatives and friends.