During July 19, the following activities were held:
- works on walls reinforcement are held;
- with the cumulative total, 58 windows have been repaired (90% completed);
- works on electricity supply recovery in the left wing of the second entrance are held;
- works on cleaning up the walls on the staircase and the front; painting works of the staircase.
96 people, including 23 children, live in a temporary accommodation center on the basis of “KamAZ” hotel. Three meals a day are provided. 24 people, including 2 children, are accommodated in relatives and friends.